What year were Pre-Engineered Buildings first introduced in India by Interarch?
   
 
  Pre-Engineered buildings were introduced in the Indian market by Interarch in the year 1996 for the first time in India .

The first pre-Engineered building was Engineered & Delivered for ITC Filtrona, in Bangalore

Congratulations to Winners of our Trivia Question - Mr. Ashish Kalra & Mr. Chetan Prakash Arya
  • Kindly click on like button and then give your answers

Technical Spotlight: Sunita Hydrocolloids Pvt. Ltd.
     
  Interarch is engineering, manufacturing and delivering the first Guar Gum Buildings Project in India, till now no project has been delivered with Pre-Engineered technology in this industry. Till date all construction in this process industry have been delivered in RCC only due to complexity of the buildings but for the first time after complex engineering and innovative design Interarch has been awarded the project of new manufacturing plant of Sunita hydrocolloids at Jodhpur, Rajasthan

This building will be utilized as a process plant for making Guar Gum powder. There are 6 different units or towers in this project. Each tower has a 3 level Mezzanine floor with deck panel with floor opening for equipment pipeline.

Total height of each tower is 15.3 M. The most important aspect of this project is that in this project all the towers will be covered by a single shed of 33M clear span and a clear height of 23M.

Interarch further connected all the towers internally by walkway thereby giving it a one point access. One can travel through all the towers & floors.

Industrial louvers have also been installed for proper ventilation. Each wall has a Liner panel with insulation.

Each floor is designed for Static as well as Dynamic loading that to without Cross Bracing and all Mezzanines with Bi-directional force transmission with Mezzanine beam.
This project is designed according to the latest IS design code (IS 800:2007) with consideration given to all the geographical data like wind velocity, seismic zone as per IS standard for particular site.





 
  Project Spotlight:
Project Name Sunita Hydrocolloids
Site Location Jodhpur, Rajasthan
Building Usages Process plant for the production of Guar Gum Powder.
Design Code Latest IS design code IS 800:2007
Project Area 2400 Sq. M
Total Tonnage 650 Ton
Special Features 6 Tower Building with G+3 Mezzanine floor (Total height 15.3m of each Tower)
Covering Shed with clear span of 33 M & Clear height of 23M.
Complex Structure made in consideration for both Static & Dynamic load
Wall liner with Industrial louvers
Fully Insulated building with Fiberglass at wall and Polynum at Roof.

 
Trivia Question of the Month: September
 
 
  Q1. How many Quality checks are conducted in a manufacturing process of Pre- Engineered Building by Interarch
  • DI + VI + UT + DP + DFT
  • VI + UT + DP + DFT
  • UT + DP + DFT + DI
  • DP + DFT + DI + VI
  • DI + VI + UT + DP
Kindly log on to http://www.facebook.com/interarchbuildings and provide the correct answer Winner will be announced in next month newsletter
 
     
Interarch Contribution to Environment: Goals of Green Buildings
     
  Green building brings together a vast array of practices, techniques, and skills to reduce and ultimately eliminate the impacts of buildings on the environment and on human health. It often emphasizes taking advantage of renewable resources, e.g., using sunlight through passive solar, active solar, and photovoltaic techniques and using plants and trees through green roofs, rain gardens, and reduction of rainwater run-off. Many other techniques are used, such as using wood as a building material, or using packed gravel or permeable concrete instead of conventional concrete or asphalt to enhance replenishment of ground water.

While the practices, or technologies, employed in green building are constantly evolving and may differ from region to region, fundamental principles persist from which the method is derived:
Siting and Structure Design Efficiency, Energy Efficiency, Water Efficiency, Materials Efficiency,
Indoor Environmental Quality Enhancement, Operations and Maintenance Optimization, and
Waste and Toxics Reduction. The essence of green building is an optimization of one or
more of these principles. Also, with the proper synergistic design, individual green building technologies may work together to produce a greater cumulative effect.





Delivering Value Vikas kaushal, Vice President-Marketing, Interarch Building Products
     
 

Time comparison between Pre-Engineered Buildings & Conventional method of Construction

Time & Schedule Comparison between Pre-engineered steel building and conventional method of construction: For a 50000sqft warehouse or factory building: (Does not include foundations and other associated works)



Activity Conventional RCC / Site fabrication system
(A)
Pre-engineered steel Building system.
(B)
Time Saving
(A-B)
Finalization of Building concept and layout 4 weeks 2 weeks - with inputs from PEB company. 2 weeks
Preparation of approval drawings. 2 weeks 2 weeks Nil
Preparation of BOQ & fabrication / site execution drawings 6 weeks 2 weeks 4 weeks
Sourcing of material 6 weeks Nil with existing plant inventory. 6 weeks
Actual Fabrication / Construction at site/plant 10 weeks at site 6 weeks under controlled plant environment. 4 weeks
Final Site execution 14 weeks 10 weeks 4 weeks
Total Schedule 42 weeks 22 weeks 20 weeks

 
 
For example if the rent on warehouse is approximately Rs.10/Sqft / Month

By adopting a Pre-engineered steel construction method the owner can get benefited by:

50000Sqft x Rs.10/Sqft x 5months (20 weeks) = Rs.25,00,000/- approximately

There will be some deduction in terms of interest on early investment but it will be neg-
ligible in comparison to the overall earning. Similarly for any manufacturing process, the increment in terms of early return on investment can be calculated based on the input
cost, product cost and margins on sales price.

The above schedule may vary depending upon the complexity and other projects requirements however the overall saving in time remains approximately in tune of 30 to
40 % as compared to any other method of construction.

Customer Testimonial: Madhu Hydrocolloids Pvt. Ltd.
     
  We appreciate the effort put in totality by INTERARCH’s team at all stages, resources deployed and cooperation extended for the satisfactory and timely completion of the project. And also special appreciation for the project head (Mr. Raja Anil Sharma) & his crew (Mr. Dhaval Patel) deployed over the project for putting their best efforts, sincere contribution, and timely response as per need to give a smooth finish to the project in a particular time frame. We wish them success for all their coming future assignments.

 
     

Major Project Wins

  • Bilt Graphic Paper Product Ltd
  • Ultratech Limited
  • Bridgestone India Pvt Ltd
  • Envirotech Systems Pvt Ltd
  • Macro Engineers
  • Utkal Alumina International Ltd



Major Projects Completed

  • M/s Jaideep Ispat & Alloys Pvt. Ltd, Pithampur
  • SMCC Construction India Ltd, Bawal
  • Kent RO Systems Ltd, Roorkee
  • M/s Wockhardt Ltd, Aurangabad
  • Anjaneya Storage & Warehouse India Ltd, Bangalore

Interarch In Press

  • Construction World
  • Steel Structure & Metal Buildings
  • Engineering Procurement & Construction




Did You Know: Stringent Safety Precautions Taken by Interarch at Site
 
  • All sites to have a Safety Officer
  • Personal Protective Equipment: Safety shoes and safety helmet are mandatory to enter the work site. Other safety equipment’s like safety belt, safety gloves and safety goggles to be worn as applicable for site work.
  • Life line and safety nets and personal safety belt to be used for working on heights.
  • All lifting equipment’s to have valid registration, insurance and calibration certificate.
  • All drivers/operators to have suitable experience and valid license papers.
  • A daily ‘Tool Box Talk’ to be conducted before the start of work.
  • Availability of First Aid Box on site with required medicines.



 

INTERARCH BUILDING PRODUCTS PVT. LTD., Central Marketing Office, B-30, Sector 57, NOIDA - 201 301, INDIA
Tel.: +91-120-4170200, 2581029, Fax: +91-120-2581017, E-mail: info@interarchbuildings.com
visit us at: www.interarchbuildings.com www.facebook.com/interarchbuildings