Tata Motors, Dharwad

With past history of more than 2 decades and delivery of more than 5 Green field manufacturing projects and over 100 buildings for Tata motors, Interarch delivered a manufacturing facility for TATA MOTORS in Dharwad. Tata motors wanted to construct this plant not only in record time to carter the growing demand of the mini truck , but also wanted the state of the art manufacturing facility to be built with Green building norms. After completion this is the first Green "Greenfield automotive project" in the history of the company and India.

Project Highlights:

  • Building Location: Dharwad, Karnataka
  • Building Usage: Manufacturing Facility
  • Tonnage of building: 5400 MT
  • Roofing Supplied in MT: 83,000 Sq. M
  • Value of Project: 86 Cr.
  • Area of Project: 72,000 Sq. M
  • Important Feature of Project:
    • Complete factory will designed and manufactured under the norms of Green Buildings
    • Multilevel mezzanines with heavy collateral load for paint equipment installations
    • IS-1984 designed building structure with heavy collateral loading to meet all manufacturing and MEP support needs
    • Regular Quality check and action jointly with client to achieve best quality in line with global standard
    • Site roll forming for entire roofing, cladding, liner etc. for faster manufacturing and Quality control
    • Highest level of safety standard achieving zero accident with 500 semiskilled and unskilled labours at the peak time
    • No. of Buildings - 11
    • Manpower deployed - 500

Delhi International Airport IGI -Terminal 3 project

Interarch was chosen amongst many international and Indian-JV bidders from an international bidding process, to come aboard under lead contractors Larsen & Tubro and GMR-DIAL, to execute the structural steel works for the Domestic and International Piers of the Delhi International Airport IGI -Terminal 3 project as well as the entire roofing system for the entire terminal building.

Through its course Interarch designed, manufactured and constructed over 7500 MT of steel in under 8 months and designed, procured and lay over 1.2 million square meters of roofing material to cover one of the largest buildings in Asia.

  • Building Tonnage: 7200MT
  • Covered Area: 175,000 Sq. M
  • Building Usage: Airport Terminal & Piers

Project Highlights:

  • High end roofing designed for over 75 years life guarantee
  • Challenges with various interfaces
  • Highest level of safety & EHS condition
  • Worked with structural consultants and architect